KUT Sewerage system

:
Ministry of Public Works

:
Iraq

:
Jan, 2008

:
Prime Contractor

:
Design-Build

:
$ 19.0 million

:
Waste Water


:

The Project includes design, supply, Erection, supervision & Construction Management of turnkey sewage treatment plant of capacity 24000m3/day, including Drainage scheme collection, pumping & conveyanceSewage treatment plant with average capacity of 24000 m3/day and peak capacity of 62500 m3/day
3 Screw lifting stations with capacities of 572 – 2034 m3/hr
3 storm water lifting stations with capacities of 792-1224 m3/hr
The Civil works were already constructed using the consultants original design drawings before tendering and awarding of KUT contract without prior coordination with El Concorde Construction. Accordingly, the equipment’s installation, many site modification/ reconstruction of certain parts were applied to suit the equipment’s