Rehabilitation of Greater Amman Water Supply System (Contract No 12)

:
Water Authority of Jordan

:
Jordan

:
August, 2001

:
April, 2005

:
Prime Contractor

:
Construction

:
$ 11.0 million

:

• Contract # 12 is located mainly in the north- east of Amman including Nuzha and Tabarbour distribution zones.
• Laying of D.I pipes ranging in size from 80 DN to 300 DN and totaling in length to almost 52000 m
• Laying of P.E pipes ranging in size from 25 DN to 63 DN and totaling in length to almost 53000 m
• Laying of galvanized pipes from ranging in size from 1/2" to 2" and totaling in length to almost 65000 m
• Construction of a new reservoir at Al Nasr with a capacity of 10000 m3 in addition to the construction a chlorination building at the same location
• Construction of a new reservoir at Qala'a with a capacity of 10000 m3
• Construction of a new reservoir at Tabarbour with a capacity of 4000 m3